French auditors warn cheap electricity could strain EPR2 funding
From the Energy digest for Nov 16, 2026
Sources World Nuclear News published Nov 16, 11:05 AM ET
What happened: France's state audit office, the Cour des Comptes, says EDF could struggle to fund its planned construction of six EPR2 reactors, putting the programme in a new report at EUR84 billion (about USD 92 billion) at 2025 values — up from EDF's December 2025 estimate of EUR72.8 billion (USD 80.1 billion). The reactors are planned at Penly, Gravelines and Bugey, with construction pencilled in to start in 2027.
What's genuinely new: The report on state support for energy production warns that at electricity prices below EUR70/MWh, EDF's financing requirements would rise significantly, potentially forcing the state to forgo dividends and costing public finances by as much as EUR65 billion cumulatively between 2026 and 2040. The contract-for-difference mechanism would carry no budgetary impact until first commissioning, at the earliest in 2038. The European Commission's in-depth state-aid investigation, opened in April, continues.
Watch: The state-aid investigation's outcome, electricity prices against the EUR70/MWh threshold, Penly's 2027 construction start.