Rosatom: Akkuyu 1 nears fuel loading in Turkey while Hungary audits Paks II
From the Energy digest for Nov 16, 2026
Sources World Nuclear News World Nuclear News, link 2 published Nov 16, 8:18 AM ET
What happened: Two of Rosatom's export projects are at decision points. In Turkey, Akkuyu unit 1 is preparing for hot tests, and Rosatom director general Alexei Likhachev hopes loading real fuel into the first reactor vessel could begin in December, with nuclear electricity following in January–February 2027. In Hungary, construction of the Paks II plant continues while the government's review of the whole project runs on.
What's genuinely new: Speaking at COP31 in Turkey, Likhachev set the December fuel-loading hope and said Turkish entities have expressed interest in taking investor stakes of up to 49% at Akkuyu under confidential negotiations; the plant also hosted a pre-start-up World Association of Nuclear Operators peer review by 17 experts. On Paks II, Paks II CEO Attila Sagody says the audit — launched under Prime Minister Peter Magyar's government after first concrete was poured in February — should complete by the end of this year, while Rosatom says it is willing to provide clarifications and prepares its work programme for next year.
Watch: December fuel loading and January–February first power at Akkuyu 1, potential Turkish investors, the Hungarian audit's outcome, Paks II's 2026 work programme.