Oklo's Groves-1 isotope test reactor

Open · 2 updates · since · updated Energy nuclear us Arc · Advanced nuclear online

Department of Energy clears Oklo's Groves-1 test reactor for unrestricted operations
AI image

Where it stands: Oklo's Groves-1 isotope test reactor reached substantial construction completion in 229 days, at about $65 million plus roughly $10 million for commercially sourced fuel. The Department of Energy has cleared its final operations hold point, moving it into unrestricted research, testing and training operations. Oklo expects a first contracted isotope delivery within 12 months; next watch Groves-2 construction and delivery timing.