Mochovce 4 reaches 35% power as commissioning advances
From the Energy digest for Nov 12, 2026
Sources World Nuclear News published Nov 12, 6:55 AM ET
What happened: The fourth unit at Slovakia's Mochovce plant has had its power output raised to 35 percent, up from about 20 percent at its first grid connection in October, after a series of tests and measurements. Checks repeat at 35 percent before output rises in stages to 55, 75, 90 and 100 percent; the final commissioning step for the 471-MWe unit is a 144-hour trial run at full power.
What's genuinely new: The unit has generated about 16.2 GWh so far — equivalent to roughly a year's electricity for 6,500 households — and clears the next rung of the energy start-up program. The 471-MWe unit equals about 13 percent of Slovakia's current consumption; sister unit Mochovce 3 entered commercial operation in October 2023.
Watch: the test program at 35 percent, the staged increases, and the 144-hour full-power trial run.