Akkuyu unit 1 containment passes strength and leak tests
From the Energy digest for Nov 13, 2026
Sources World Nuclear News published Nov 13, 5:33 AM ET
What happened: Turkey's first nuclear power unit — Rosatom's VVER-1200 at Akkuyu, being built under a build-own-operate model — completed eight-day pre-start-up strength and leak tests on its internal containment building. Air pressure was raised to 0.46 MPa, a load equivalent to about 47 tonnes per square metre, then reduced in stages including below atmospheric, with leak-tightness checked at both elevated and reduced pressure.
What's genuinely new: Akkuyu Nuclear JSC says the results clear the unit for the next commissioning stage: cold and hot functional testing of the reactor plant. Unit 1's target remains first grid supply by the end of 2026, and the 4,800-MWe four-unit plant is meant to meet about 10% of Turkey's electricity needs; Turkey also aims to add 5 GWe of small-modular-reactor capacity by the equivalent of at least 16 units by 2050.
Watch: cold and hot functional testing at unit 1, and first grid supply against the end-2026 target.