Akkuyu 1 enters commissioning testing ahead of planned start-up
From the Energy digest for Nov 19, 2026
Sources World Nuclear News published Nov 19, 5:46 AM ET
What happened: Turkey's first nuclear reactor, Akkuyu unit 1, has moved into hot and cold commissioning tests: equipment in the primary and secondary circuits is being checked under operating conditions — strength, piping, vibration, safety and reactor control systems — with dummy fuel assemblies loaded. The primary coolant is being brought to its rated 285°C and 16.5 MPa.
What's genuinely new: After the tests, Turkey's nuclear regulator must inspect the unit and grant a permit for real fuel loading before physical start-up. Rosatom director general Alexei Likhachev, quoted through Rosatom's in-house publication, hopes fuel loading can begin as early as December if the tests succeed, with unit 1 targeted to supply the Turkish grid by the end of 2026. The four-reactor, 4,800-MWe build-own-operate plant is expected to meet about 10% of Turkey's electricity needs when complete.
Watch: Test outcomes, the regulator's fuel-loading permit, and Turkey's talks with Canada and South Korea about further reactor projects.