Bangladesh gets its first nuclear electricity as Rooppur 1 connects to the grid
From the Energy digest for Nov 19, 2026
Sources American Nuclear Society published Nov 19, 8:44 AM ET
What happened: Unit 1 of the Rooppur nuclear power plant fed electricity into Bangladesh's national grid for the first time on November 17, with initial output reaching 350 MW and lasting 8 to 10 hours, according to state-owned Power Grid Bangladesh. Science and technology minister Fakir Mahbub Anam said the country has become the 33rd nation to generate nuclear power.
What's genuinely new: The November 17 output was a grid-synchronisation test run — an engineering check of voltage, frequency, the turbine and other systems, not commercial generation. The Russian-built and -financed 1,200-MWe VVER-1200 reached criticality in October, and plant managing director Zahedul Hasan says checks will continue at various capacity levels for several months, with regulator approval required before the next phase of trials. Full capacity is expected in early 2027, commercial operations after about 10 months of trial runs, and fuel loading of unit 2 by June 2027.
Watch: Regulator approval of the next operational trials, capacity escalation toward the 2027 commercial start, and unit 2's fuel-loading progress.