Poland takes the next procurement step on its first nuclear plant
From the Energy digest for Nov 20, 2026
Sources World Nuclear News
What happened: State developer Polskie Elektrownie Jądrowe signed a letter of intent with the Westinghouse-Bechtel consortium to extend the scope of the Engineering Development Agreement to cover procurement of long-lead items for the first of three AP1000 reactors at the Lubiatowo-Kopalino site in Pomerania. The letter was signed at the Partnership for Transatlantic Energy Cooperation ministerial meeting in Warsaw, and the US partners will also support PEJ in negotiations with export credit agencies on financing the component supply.
What's genuinely new: The framework for widening the long-lead ordering, on top of the ordering already under way: Westinghouse has placed conditional purchase orders with Polish fabricators Energomontaż-Północ Gdynia, FAMAK, Mostostal Kielce and Mostostal Kraków for containment-vessel wall, floor and module scopes, and Japanese firm IHI Corporation received an order covering engineering and procurement for one containment vessel and a large steel module. Bechtel, Gdańsk University of Technology and the University of South Carolina also signed a nuclear workforce memorandum.
Watch: The construction (EPC) contract, export-credit-agency financing and further long-lead orders and module fabrication.