Steam generators delivered for Leningrad II's third unit as MBIR hardware completes
From the Energy digest for Nov 25, 2026
Sources World Nuclear News published Nov 25, 5:28 AM ET
What happened: Rosatom says four steam generators — 13 metres long, 4.2 metres in diameter, more than 1,300 tonnes combined — have been delivered for the third unit of the Leningrad II phase, ready for inspection before installation at their design positions; eight supports are planned by spring 2027, and the unit's reactor vessel is slated for installation in the third quarter of 2027. Two completed reverse steam generators were also shipped for the MBIR, a 150-MWt fast research reactor at Dimitrovgrad scheduled to start up in 2027, replacing the BOR-60.
What's genuinely new: The deliveries themselves at two Rosatom builds. Leningrad II's first two VVER-1200 units were commissioned in 2018 and 2021; the third and fourth now under construction will replace the site's four RBMK-1000 units, with third-unit concrete poured in March 2024. The MBIR steam generators follow the reverse-flow design proven on BOR-60, which has operated on the site since 1969.
Watch: Leningrad II unit 3's 2027 installation programme and MBIR's start.