SR-1 Freedom space reactor
Where it stands: NASA's SR-1 Freedom is a planned Idaho National Laboratory-led space reactor, meant to be the first demonstration of nuclear propulsion in space and set to launch in 2028. It would start up for about seven days, shut down while its Skyfall payload travels to Mars, then restart for testing. NASA has also issued a request for proposals for Lunar Reactor-1, a 20-kilowatt lunar-surface reactor due to be launch-ready by December 2030, with proposals due December 21. Watch for the VALKRE test reactor at INL, scheduled to go critical in summer 2027.
Latest
- NASA says it has decided key design features and mission details for SR-1 Freedom, the first fission-powered spacecraft to travel beyond Earth orbit — set to launch in 2028 to demonstrate nuclear electric propulsion in deep space. Development of the reactor program; watch: launch-schedule firming, the ground-test campaign, and the LR-1 lunar reactor tender feeding the same development line.
AI image NASA — x.com/NASA
- Headline: SR-1 Freedom space reactor — Panels at the American Nuclear Society Winter Conference detailed SR-1 Freedom, the Idaho National Laboratory-led program aiming at the first demonstration of nuclear propulsion in space: after launch the reactor starts up from Johnson Space Center — a DOE reactor operator alongside a NASA operator, about seven days for startup and checks — then shuts down until the Skyfall payload is delivered to Mars and restarts for testing that may include purposely failing components; control is automated with human stopping points, not autonomous (American Nuclear Society). The VALKRE test reactor at INL, run with flight control hardware to the zero-criticality point, is scheduled to go critical in the summer of 2027; SR-1 itself gets an engineering demonstration unit and zero-power criticality testing at INL, and NASA Administrator Jared Isaacman has called SR-1 a "70 percent solution to prove that it works." SR-1 is designed to support the lunar LR-1 reactor and a later SR-2 mission. Watch: VALKRE's summer 2027 criticality, the ground-test campaign, and the SR-1 launch schedule.
AI image
Images in this thread
Claims to watch · 3 (3 pending, 0 slipped, 0 hit, 0 missed)
- Vivek Agarwal, Nov 23, 2026: VALKRE criticality due pending Source
checked Nov 24, 2026: At the American Nuclear Society's 2026 Winter Conference, SR-1 Freedom instrumentation and controls lead Vivek Agarwal said the VALKRE test reactor at Idaho National Laboratory is scheduled to go critical in the summer of 2027 and that flight systems will operate it to the zero-criticality point, with nothing since reporting a change to that schedule. Source - NASA, Nov 24, 2026: SR-1 Freedom launch due pending Source
- NASA, Nov 24, 2026: LR-1 launch-ready due pending Source
Background
2026-11-24: NASA opened bidding for Lunar Reactor-1 (LR-1), the 20-kilowatt fission reactor for the lunar surface — designed to launch by 2030 and supply continuous electricity for at least five years across the roughly 14-Earth-day lunar night and in permanently shadowed polar craters — with proposals due December 21 under a framework co-managed with the Department of Energy (Stocktwits; Jeff Foust RT of NASA). Program manager Brian Giblin called reliable, abundant energy vital to future lunar and Martian exploration. Space and nuclear equities rallied on the announcement. Watch: bidders and winners, how LR-1 draws on SR-1's development line, and the 2030 launch-ready date.
2026-11-24: the RFP layer — NASA issued a request for proposals for Lunar Reactor-1 (LR-1), the 20-kilowatt lunar-surface fission system: launch-ready by December 2030, closed Brayton conversion with HALEU, a habitable zone one kilometre out shielded to at most 5 rem above lunar background per year, at least five years of maintenance-free operation through 14.75-day polar darkness, DOE-STD-1271 authorization, and 18-month contractor scopes building a nonnuclear Engineering Test Unit in a thermal-vacuum environment; task orders may extend to other space nuclear power systems (ANS). The November 23 ANS Winter Conference panel framed LR-1 as a downstream user of SR-1 Freedom's development line, and both are run from NASA's Space Reactors Division, with SR-1's 2028 launch expected to yield data supporting LR-1. Watch: contract awards and SR-1's launch schedule.