Darlington's first BWRX-300 slips past October 2030 and its CAD 7.7 billion budget
From the Energy digest for Nov 11, 2026
Sources World Nuclear News Canary Media published Nov 11, 2:00 PM ET
What happened: Ontario Power Generation says the first of four GE Vernova Hitachi BWRX-300 small modular reactors at the Darlington New Nuclear Project east of Toronto will no longer reach commercial operation by the previously disclosed target of October 2030, nor be completed within the previously estimated CAD 7.7 billion (US$5.4 billion). No new targets were shared — a comprehensive reassessment of unit 1's cost and schedule is under way, to be substantially complete by mid-2027.
What's genuinely new: The disclosure came in OPG's third-quarter 2026 results, and it is the project's second slip: when OPG announced the design in late 2021, it said the reactor could be completed as early as 2028. OPG attributes the slip to GE Vernova Hitachi's ongoing engineering for its first-of-a-kind design, which affects construction execution and supply-chain performance, with updated market conditions — inflationary and geopolitical risk — also weighing. Unit 1 would be the first new nuclear build in Canada in more than three decades; the CNSC issued the construction licence in April 2025, Ontario approved the CAD 20.9 billion (US$15 billion) four-unit budget and construction start the following month, and federal and provincial funds have since committed up to CAD 3 billion (about US$2.1 billion) for minority stakes. GE Vernova Hitachi spokesperson Jonathan Allen pointed to "multiple interconnected contributions" across engineering, procurement and construction. Canary Media adds the wider stakes: the TVA received an NRC construction permit for a BWRX-300 in September and developer Blue Energy has started an NRC application for one in Texas, only two SMR plants operate commercially worldwide (in Russia and China), and the last large US nuclear build — Georgia Power's Vogtle units 3 and 4 — ran seven years late and US$17 billion over.
Watch: The revised cost and schedule outlook by mid-2027, completion of the outstanding engineering scope, and whether the overruns chill the other BWRX-300 projects in flight.