Darlington BWRX-300

Open · since · updated Energy nuclear smr ge-vernova-hitachi

Ottawa defends its Darlington SMR stake as cost and schedule slip
AI image

Where it stands: Ontario Power Generation says the first of four BWRX-300 reactors at its Darlington New Nuclear Project will miss both its October 2030 commercial-operation target and its CAD 7.7 billion cost estimate, citing first-of-a-kind engineering, supply-chain performance, inflation and geopolitical risk. Critical construction work continues on site. Watch for a comprehensive cost-and-schedule reassessment due to be substantially complete by mid-2027.

Images in this thread

Claims to watch · 1 (1 pending, 0 slipped, 0 hit, 0 missed)
  • Ontario Power Generation, Nov 10, 2026: Unit 1 cost and schedule assessment substantially complete by mid-2027 due pending Source

All tracked claims

2026-11-11: Ontario Power Generation says the first of four BWRX-300s at the Darlington New Nuclear Project will miss both the previously disclosed October 2030 commercial-operation target and the CAD 7.7 billion (USD 5.4 billion) estimated cost — GE Vernova Hitachi's ongoing engineering for its first-of-a-kind SMR is affecting construction execution and supply-chain performance, with updated inflationary and geopolitical market risk also cited; a comprehensive cost-and-schedule reassessment is to be substantially complete by mid-2027. OPG CEO Nicolle Butcher says critical work continues on site but risks affecting Unit 1's schedule and budget have been identified; GE Vernova Hitachi spokesperson Jonathan Allen cites "multiple interconnected contributions" across engineering, procurement and construction (World Nuclear News). Context: CNSC licence to construct April 2025; Ontario approved the CAD 20.9 billion (USD 15 billion) four-unit budget and construction start the following month; the Basemat foundation module was set in place in April. Watch: the revised outlook by mid-2027, completion of outstanding engineering scope, and effects on the broader BWRX-300 pipeline.