Ottawa defends its Darlington SMR stake as cost and schedule slip

Energy nuclear smr ge-vernova-hitachi

From the Energy digest for Nov 14, 2026

Ottawa defends its Darlington SMR stake as cost and schedule slip
AI image

Continuing thread: Darlington BWRX-300

Sources The Globe and Mail Power Engineering OPG

What happened: Canada's energy minister is defending the federal government's $2-billion equity investment in Ontario's Darlington small modular reactor after Ontario Power Generation confirmed the first of four planned BWRX-300 reactors will miss both its October 2030 completion target and its C$7.7-billion (US$5.5 billion) budget. Energy Minister Tim Hodgson called the setbacks "a reality in all first-of-a-kind projects," saying it is important that Canada "not balk" on such investments. GE Vernova Hitachi, whose ongoing engineering on the first-of-a-kind design OPG blamed, says inflation and geopolitical risks contributed too.

What's genuinely new: The federal risk-sharing mechanics are now on the table: the Canada Growth Fund says its capital deploys in two tranches tied to project milestones — one for the first reactor unit, one for the remaining three — and Hodgson says "on and off ramps" protect the fund. Power Engineering adds spending detail: C$2.86 billion (US$2 billion) spent through September 30, about 37 percent of the C$6.1-billion Unit 1 allocation within the C$20.9-billion (US$15 billion) four-unit project, with cooling-water-tunnel excavation to begin in Q4 2026. OPG has also withdrawn most of its requested Darlington approvals from its Ontario Energy Board rate application for 2027–2031, with costs instead tracked through variance accounts subject to review.

Watch: OPG's revised cost and schedule, with its comprehensive assessment expected substantially complete by mid-2027; the Ontario Energy Board's handling of the withdrawn rate-case approvals; and whether the reassessment reshapes cost assumptions for the wider BWRX-300 pipeline.

More context: OPG says its Darlington Unit 1 reactor is no longer expected to hit its October 2030 commercial operation date or its C$7.7-billion cost estimate, which includes systems and services shared with the three units to follow, citing GE Vernova Hitachi's unfinished engineering on the first-of-a-kind design.

Next: NRC review of Orano's Project Ike enrichment plant slips to mid-2027