India: RAPP-8 cleared for first criticality, Kaiga 1 restarts after a 600-day refurbishment
From the Energy digest for Nov 24, 2026
Sources World Nuclear News published Nov 24, 12:10 PM ET
What happened: India's regulator, the Atomic Energy Regulatory Board, cleared Nuclear Power Corporation of India's RAPP unit 8 — a 700-MWe pressurised heavy water reactor at the Rajasthan Atomic Power Project — for its First Approach to Criticality on November 19, after safety reviews and inspections. Fuel loading began there on September 19. Kaiga unit 1, a 200-MWe reactor first connected to the grid in 2000, returned to criticality on November 22 after a full refurbishment shutdown that began April 1, 2025.
What's genuinely new: Kaiga 1's coolant-channel and feeder replacement took 600 days — a fleet-wide benchmark, NPCIL says, and the first of its reactors to reach criticality that soon after such an outage. RAPP-8 is the second of a 700-MWe pair at Rajasthan and the fourth of sixteen such units being built; its neighbour RAPP-7 reached full power in 2026 after first criticality in September 2024 and grid connection in March 2025.
Watch: RAPP-8's criticality, commissioning tests and regulatory permissions on the path to commercial generation.