US uranium output slumped 78% in Q3 as White Mesa readies a December restart
From the Energy digest for Nov 24, 2026
Sources World Nuclear News EIA published Nov 24, 5:22 AM ET
What happened: US production of uranium concentrate fell 78% in the third quarter of 2026, to 243,673 pounds U3O8 (about 110.5 metric tonnes), per the Energy Information Administration. The drop was driven by the pause at Energy Fuels' White Mesa mill in southern Utah, the only operating conventional uranium mill in the US, which stopped uranium processing in June after hitting its 2026 guidance to rebuild ore inventory and switch to rare-earth processing. Eight in-situ recovery plants in Wyoming, Texas and Nebraska kept producing.
What's genuinely new: Energy Fuels plans a large-scale uranium campaign beginning in December 2026, expected to produce about 1 million pounds U3O8 and support contract deliveries through 2028, before the mill returns mostly to rare-earth processing through much of 2027–2028. It still expects 1.6–2.0 million pounds total for 2026 and is advancing Whirlwind (nearly production-ready, first output scheduled for 2028, in Colorado on the Colorado–Utah border about 150 miles north of the White Mesa mill), with Energy Queen and Bullfrog in Utah plus drilling at Nichols Ranch, Wyoming — together capable of about 1.25 million pounds a year.
Watch: The December campaign volumes, Whirlwind's permitting and 2028 start, and a possible Nichols Ranch restart, as Pinyon Plain winds down.
More context: The EIA reports that third-quarter 2026 US uranium concentrate output of 243,673 pounds U3O8 was a 78% fall from the 1,087,504 pounds produced in the second quarter, all of it from eight in-situ recovery facilities in Wyoming, Texas and Nebraska.